ADR 0002 — Implement EPICs by dependency, not number

Architecture decision record — status: Accepted.

Status: Accepted

Decision#

The dependency graph in scripts/tracker.mjs (DEPENDENCIES) drives order. Security-critical foundations (tenancy, identity, authorization, policy, risk, approvals, vault, execution) come before breadth (connectors, runtimes, UI). Several EPICs were pulled forward because others depend on them:

  • EPIC 13 (delegation) with EPIC 4 — authentication must validate delegated tokens.
  • EPIC 21 (audit chain) with EPIC 2 — every change is audited from the first commit.
  • EPIC 33 (event platform) with EPIC 7 — approval notifications are events.

Consequences#

Completion is tracked per deliverable with evidence in docs/tracker/; only VERIFIED counts as complete.